ECONOMY
11:58

Another extension to net metering: Who is affected and when must the procedures be completed?

Changes to pending applications and the need to establish uniform safety standards for residential batteries
ALPHANEWSLIVE


The Cyprus Electricity Authority granted a three-month extension for the completion of pending procedures related to net metering applications, in response to requests from consumers and trade associations, so that the necessary checks can be carried out and those who have already submitted an application do not risk losing access to this system.

Speaking on the Alpha Kalimera program, Electrical Engineer Yiannis Tsigaridis clarified that the extension does not apply to new applications, but to existing ones submitted in 2025 and earlier. As he explained, the original deadline for submitting plans to the EAC, so that the necessary review could be conducted, was November 27. With the extension, the deadline has been moved to February 28, while the checks are expected to be completed by September 14, 2027.

Mr. Tsigaridis expressed his satisfaction with the EAC’s response, noting that thousands of applications had piled up and that the delays were due both to the increased workload and to practical difficulties faced by households. As he noted, in many cases consumers needed more time to raise the funds required for installation, while others had not yet completed the work on their homes. At the same time, the summer vacation and Christmas periods further slowed down the process.

According to him, the backlog of applications had caused delays of about two to three months at various stages, ranging from the work of contractors and electricians to the EAC’s inspections. He estimated that with the new timeline, pending issues will be resolved smoothly, without further burdening consumers with new applications and repeated procedures.

What’s Changing with Net Billing

The electrical engineer noted that net metering—that is, the offsetting of kilowatt-hours— allowed consumers to feed excess energy generated by their solar panels back into the grid and have it credited as kilowatt-hours on their electricity bills.

This system was in effect until the end of 2025, while new photovoltaic installations now operate under the net billing method. As he explained, there are two scenarios: either the surplus energy is credited to the consumer as a monetary amount, or, in areas where the grid is saturated, the “zero export” option is applied, meaning that energy cannot be fed into the grid.

In the second case, as he pointed out, batteries must be installed to store the energy that cannot be fed into the grid.

Calls for a unified framework for battery safety

Mr. Tsigaridis also raised the issue of establishing uniform rules for the installation and operation of residential energy storage systems. As he noted, it is necessary for the Ministry of the Interior to examine the issue and issue a joint circular or guide that will specify the technical specifications and standards that must be followed, so that installations can be carried out safely. He clarified that battery technology is quite safe, provided that the installation is performed correctly and the prescribed procedures are followed.

He emphasized, however, that responsibility does not end with installation, as ongoing monitoring and maintenance are also required. As he pointed out, unlike photovoltaic systems, which until now have operated without requiring continuous monitoring by the consumer, batteries need regular monitoring and maintenance.